Performed works:
— Functioning as the head commissioning contractor.
— Commissioning of heat and electrical equipment.
— Commissioning of general plant systems, commissioning of boiler make-up equipment.
— Guarantee testing of CCP in terms of gas turbine and steam turbine units, heat recovery boiler.
— Training and preparation of operating personnel.
Equipment:
— Gas turbines SGT5-4000F manufactured by Siemens.
— Generators Sgen5-1000A manufactured by Siemens.
— Steam turbine K-130 manufactured by Power Machines JSC.
— Heat recovery boiler manufactured by IK ZIOMAR OJSC.