Performed works:
— Functioning as the head commissioning contractor.
— Commissioning of the main and auxiliary equipment of four combined cycle plants.
— Commissioning of water treatment equipment and chemical water treatment equipment.
— Calibration of measuring channels and verification of control circuits of shut-off and control valves.
— Adjustment of process functions of local ACS.
— commissioning of electrical equipment (6 kV complete switchgear, 0.4 kV auxiliary switchgear, outdoor 110 kV switchgear)
— Warranty testing of the main equipment.
— Regime and adjustment works of main and auxiliary equipment of 4 power units
Equipment:
— Gas turbines PG6111(FA), manufactured by Russian Gas Turbines LLC.
— Generator TF-90G-2U3, manufactured by ELSIB CJSC.
— Steam turbines K-38-8.0 manufactured by Power Machines LMZ JSC.
— Heat recovery boiler manufactured by Podolsk Machine-Building Works OJSC.