Performed works:
— Functioning as the head adjusting contractor.
— Full scope of equipment commissioning for Power Unit 2 of Krasnoyarskaya CHPP-3.
— Comprehensive commissioning of 220 kV outdoor switchgear.
— Incoming control and calibration of I&C equipment in laboratory.
— Technical management of trial runs of main and auxiliary equipment. Round-the-clock supervision of leading specialists during start-up operations at the equipment.
— Comprehensive testing, certification of generating equipment, warranty testing of main equipment.
— Testing as required by SO UES JSC within the scope necessary for commissioning of the facility.
— Mode-adjustment works.
Equipment:
— Steam power boiler type E-810-13.8-560BT TKZ Krasny Kotelshchik OJSC.
— Electrical filters.
— Dry ash removal system.
— Steam turbine unit T-185/220-12,8-NG manufactured and supplied by UTZ JSC.
— Water recycling system with cooling tower.
— Turbogenerator TVF-220-2U3.
— indoor switchgear: 220 kV.
— Fuel supply equipment.
— Water treatment equipment.