Construction of a new complex for propylene production via propane dehydrogenation and propylene derivatives (DGP 2) at LLC “Zapsibneftekhim”


Information about the object


Name: Construction of a new complex for propylene production via propane dehydrogenation and propylene derivatives (DGP 2) at LLC “Zapsibneftekhim”
Address: city of Tobolsk
Time of work: Start date: December 2025 End date: Q1 2027

Completed works:


— Performing pre commissioning and commissioning works for the automation complex (field level)
— Performing pre commissioning and commissioning works for heating, ventilation and air conditioning (HVAC) systems
— Performing pre commissioning and commissioning works for the power supply system (switchgear 0.69 kV, 0.4 kV)
— Quality control and verification that construction and installation works (CIW) comply with project requirements
— Conducting inspections upon completion of construction and installation, pre commissioning, and commissioning works
— Monitoring and verifying the resolution of issues identified during inspections
— Ensuring equipment safety from the moment it is handed over for pre commissioning works (PCW) until it is put into operation
— Developing and approving programs, HVAC system diagrams (for passports), schedules, action lists, registers and other design documentation (DD), as built documentation (ABD), pre commissioning/commissioning documentation (PCD/CD), in accordance with the Client’s procedures and the requirements of the Russian Federation’s regulatory and technical documentation (RTD)
— Conducting individual tests
— Conducting integrated system testing