CJSC «Engineering Company KVARTS»
14.05.2009
Execution of commissioning works at the «Yuzhnoye Khylchuyu» facility as part of a gas turbine power plant with an installed capacity of 125 MW and high-voltage 220 kV lines with 220 kV substations (work in Arctic conditions)
LLC «Center for Operation and Commissioning»
18.12.2009
Execution of maintenance services for the equipment of the «Yuzhnoye Khylchuyu» Energy Center, which includes a gas turbine power plant with an installed capacity of 125 MW and high voltage 220 kV lines with 220 kV substations (work in Arctic conditions).
CJSC «Engineering Company KVARTS»
01.04.2010
Execution of commissioning works at the «Yuzhnoye Khylchuyu» facility as part of a gas turbine power plant with an installed capacity of 125 MW and high-voltage 220 kV lines with 220 kV substations (work in Arctic conditions).
Branch of CJSC «Intertechelectro» in Surgut
17.05.2010
Execution of commissioning works on the Siemens SGT-800 equipment as part of the construction project for Start-Up Complex No. 1 of the Gas Turbine Power Plant (GTPP) on the left bank of the Priobskoye field.
PJSC «Fortum»
01.08.2011
Execution of works for Technical Support and Supervision functions during the completion of commissioning works and comprehensive testing of the CCGT-230T power unit at Chelyabinsk CHPP-3.
PJSC «Fortum»
13.08.2013
During the construction period of Power Unit No. 1 at Nyagan GRES, works were carried out for technical support and supervision during the completion of construction and installation works (CIW), commissioning works (CW), and comprehensive testing of Power Unit No. 1 at Nyagan GRES.
PJSC «Fortum»
16.07.2014
Execution of commissioning works as part of the project for constructing two gas turbines with heat recovery boilers and life support systems for the newly installed equipment at Chelyabinsk CHPP-1.
OJSC Nizhny Novgorod Engineering Company «Atomenergoproekt»
29.08.2014
Execution of commissioning works on the equipment of the "Power Island" CCGT-420 MW as part of the construction of power unit No. 2 at Yuzhnouralskaya GRES-2.
OJSC «Electrosetservice ENES» - Ural Division
16.12.2014
Execution of commissioning works at the 500 kV Smelovskaya substation.
PJSC «Fortum»
15.01.2016
Execution of a set of commissioning works and functions as the main organization within the project for constructing the power unit CCGT-247.5 MW, Unit No. 1, and auxiliary equipment at Chelyabinsk GRES.
PJSC «Fortum»
25.07.2016
Execution of a set of commissioning works and functions as the main organization within the project for constructing the power unit CCGT-247.5 MW, Unit No. 2, and auxiliary equipment at Chelyabinsk GRES.
PJSC «Fortum»
28.03.2017
Execution of a set of commissioning works and functions as the main organization within the project for constructing the power unit CCGT-247.5 MW, Unit No. 3, and auxiliary equipment at Chelyabinsk GRES.
LLC «Inter RAO – Engineering»
15.11.2017
Execution of a set of commissioning works and functions as the main organization within the project for constructing the power unit CCGT-800 MW, Unit No. 4, at Perm GRES.
LLC «Inter RAO – Engineering»
15.11.2017
Execution of a set of commissioning works and functions as the main organization within the project for constructing the power unit CCGT 420 MW, Unit No. 12, at the "Verkhnetagilskaya GRES" branch.
OJSC «Yamal LNG»
Execution of a set of commissioning works as part of the construction project for the power plant at the Yamal LNG plant.
PJSC «Fortum»
Execution of functions as the main commissioning organization, including a set of commissioning works on electrical equipment, instrumentation, and automated process control systems at Argayash CHPP (Reconstruction of Power Unit No. 4).
LLC «Inter RAO – Engineering»
09.04.2019
Execution of a set of commissioning works and functions as the main organization at Pregolskaya TPP, with an electrical capacity of 4x110 MW, in Kaliningrad.
LLC Foreign Economic Association «Technopromexport»
Execution of a set of commissioning works and functions as the main commissioning organization at "Simferopolskaya CCGT-TPP," as part of the large-scale federal target program "Socio-Economic Development of the Republic of Crimea until 2020." "Tavricheskaya TPP" includes two CCGT-235 units.
LLC Foreign Economic Association «Technopromexport»
22.04.2019
Execution of a set of commissioning works and functions as the main commissioning organization at "Sevastopol CCGT-TPP," as part of the large-scale federal target program "Socio-Economic Development of the Republic of Crimea and the City of Sevastopol until 2020." "Balaklavskaya TPP" includes two CCGT-235 units based on the TPE-180 gas turbine installation.
PJSC «Quadra»
Execution of a set of commissioning works and functions as the main organization within the implementation of the project "Reconstruction of Voronezh CHPP-1. Construction of CCGT-223."
LLC «Second Wind Farm FRV»
08.06.2020
Execution of a set of construction, design, survey, and electrical installation works, including the supply of necessary equipment and materials, in the implementation of the construction projects "Kamensko-Krasnosulinskaya Wind Farm – Northern Site (Kamenskaya Wind Farm)" and "Kamensko-Krasnosulinskaya Wind Farm – Southern Site (Sulinskaya Wind Farm)."
LLC «Inter RAO – Engineering»
Execution of a set of commissioning works and functions as the main organization at Primorskaya TPP, with an electrical capacity of 3x65 MW, in Kaliningrad.
LLC «First Wind Farm FRV»
08.06.2020
Construction of Ulyanovsk Wind Farm with a capacity of 2x25 MW
LLC «Third Wind Farm FRV»
08.06.2020
Execution of the full range of construction, design, survey, electrical installation, and commissioning works, including the provision of equipment and materials, within the "Gukovo-1 Wind Farm" construction project.
PJSC «Fortum»
09.06.2020
Construction of a 110/35 kV substation in Ulyanovsk region
PJSC «Fortum»
09.06.2020
Construction of a wind power plant with an installed capacity of 35 MW in Ulyanovsk region
LLC «Wind Farms FRV»
14.12.2020
Execution of a set of construction and electrical installation works, including the supply of necessary equipment and materials, in the implementation of the construction projects "Salynskaya Wind Farm" and "Tselinskaya Wind Farm."
LLC «Seventh Wind Farm FRV»
10.12.2020
Execution of a set of construction, electrical installation, and commissioning works, including the supply of necessary equipment and materials, in the implementation of the first stage of the "Kazachya Wind Farm" construction project with a capacity of 50.4 MW.