Astrahanskaya WFs


Information about the object


Names:
Holmskaya WF.
Chernoyarskaya WF
Staritskaya WF
Customer: JSC RUSNANO and FORTUM
Time of work: с 10.2020 - 11.2021

Performed works:


— Comprehensive works on installation of 924 bored piles and control static testing of piles.
— Construction of foundations for 42 wind turbines with the volume of concrete 21 378 m³, assembly and storage platforms, reinforced concrete platforms for crane for wind turbines.
— 31.7 km of on-site roads.
— Landscaping, planting and technical reclamation of land plots.
— Installation of cable lines for power cable 35 kV, 0.4 kV, 75 km FOCL.
— Manufacturing, installation and commissioning, testing of the installed electrical equipment of WF control modules (as part of PR-35 kV, MSchU, ACS), DGU, creation of communication networks, PIES SOAS, CAEMS, WPU ACS, video surveillance, RACS and LSC, bird deterrence, FSS and WACS, ERS, GPSS.
— Commissioning. Complex testing of WF and experience of GPFC.
— Integration of WF systems with PICC (Delta/8) Fortum PJSC.