Performed works:
— Construction of 110/27.5/10 kV open substation with two power transformers of 40000 kV·A each.
— Telemechanisation (including installation of additional 110 kV equipment).
— Creation of the AIIS KUE system.
— Installation of RPA and ECA equipment.
— Creation of security and fire alarm system, creation of communication networks, ice detection system, professional heating system, own needs of the object, engineering networks and security systems.
— Installation of additional 110 kV equipment on the existing 110 kV outdoor switchgear